Camp Arcadia - Beach Erosion Committee

Home

Historical Information


History of Lake Michigan Water Levels

1892 to 1920s

1944 to Present

LCA Board Motions

 

History of Lake Michigan Water Levels

Because Lakes Michigan and Huron are connected by a deep water channel in the Straits of Mackinaw, the US Corps of Engineers considers them to be one lake. Since 1918, the average lake levels have been tracked from an arbitrary point used for that purpose. This allows the Corps to publish tables of the average water level in Lake Michigan/Huron on a monthly basis.
View a summary of the height above average on a montly basis.

back to top


1892 to 1920s

In 1892, Charles Starkey and other area businessmen decided that a channel should be built connecting Lake Michigan to Bar Lake, now known as Lake Arcadia. The channel was completed in 1893 and was maintained and dredged until 1906. Prior to the channel being built, there was a small natural channel into Lake Arcadia that was located to the south of the end of Lake Street. However, this natural channel could not be depended upon for getting larger ships into and out of the harbor in order to supply the Arcadia furniture factory and glassworks. Starkey built a bridge pier to the north of the natural channel and it extended out into Lake Michigan at the end of Lake Street. The original pier extended 130 feet into Lake Michigan. It was later extended to 1,000 feet. Below are links which will take you to images of the bridge pier and also the location of the natural channel according to an early plat of the Arcadia, Michigan shoreline.

http://www.arcadiami.com/Timeline/timelineearlytown.htm

http://www.arcadiami.com/Exhibits/Shipping/Pier/Pier.htm

In 1902, at the request of Starkey and other businessmen, the Army Corps of Engineers becomes involved in the harbor/channel project. Funds are requested to keep the channel open and to rebuild the piers on either side of the manmade channel. Unfortunately the funds do not come through and the channel is dredged but not repaired from 1905 until 1909.

The Rivers and Harbors Act of 1909 causes the Arcadia Harbor to be reviewed again by the Board of Engineers for Rivers and Harbors. Natural disasters destroying much of the local agricultural crop and fires, which destroyed the manufacturing plants have had a negative affect on commerce and as a result, Major Kellor of the Army Corps of Engineers recommends against further maintenance.

In 1910, representatives from the town of Arcadia continue to pursue federal funding for channel maintenance and repair. They have some success and are granted $20,000 for improvements in 1912. In 1913 the piers are repaired but not lengthened. Most of the superstructure of the northern pier is washed away and the tip of the southern pier is broken off. Additional requests for funding are made but funding is scarce and the Arcadia Harbor has been blacklisted by the Army Corps of Engineers. As a result, the piers deteriorate and eventually the channel closes in 1925 due to the natural ebb and flow of the lake. The natural channel also closes and opens sporadically and eventually all commerce from shipping ceases to exist in Arcadia.

At this point, it should be noted that sand was naturally accreting on the shoreline of Lake Michigan. Early pictures of the beach in Frank W. Miller’s book, Camp Arcadia The First Sixty Years, show what the beach looked like in the mid twenties.

back to top

1944 to Present

In 1944, the concrete pier which exists today, was built extending 75’ out into the lake in front of the Inn. Water levels were on the rise and in 1948 four jetties were built in front of the property. These jetties were extended in 1955 and four more jetties were installed. In 1957 the concrete pier was extended to 83’. The last segment of the pier has now dropped partially into the lake as a result of erosive wave and current action against the side of the pier. On page 152 of Frank Miller’s book is an aerial photo from 1957 which shows the pier and the jetties as they appeared at that time. Note the build up of extended beach to the south of the pier and the absence of beach on the northern side of the pier.

Since 1957 the Camp has fought an ongoing battle with beach erosion and high lake levels. In 1961 the Township of Arcadia and the Waterways Commission had the channel reconstructed and opened for recreational use. This only increased the Camp’s battle with erosion due to unnatural currents created by the reopening of the channel. In 1973 the Army Corps of engineers began regular dredging operations of the channel on an annual basis. From 1973 until 1978 the dredged sand was dumped in open water. In 1979, the Corps began having its contractors deposit the dredged sand to the north of the northern pier in an area from 0-2800 feet along the coastline. To view the USACE (United States Army Corps of Engineers) report on dredging activities please click on the link provided: http://www.lre.usace.army.mil/OandM/text/arcadia.pdf

In 1989, the USACE encapsulated and reconstructed both the northern and southern piers of the Arcadia Channel. Massive steel plates along with concrete and boulders were the main materials used. According to the Corps, the piers were not really extended at this time but were merely reconstructed from their 1961 configurations. The project cost just under $2,000,000 and took two construction seasons to complete the work.

back to top

Lutheran Camp Association (LCA) Board of Directors Motions

The following is a list of LCA Board motions that dealt with varying beach projects over the years with the goal of preserving our buildings.  The item numbers refer to Camp's internal number system for LCA Board motions.

1971-May 29

42. That the shore area at the tennis courts be inspected and a sea wall installed if necessary.

1973-August 16

87. To make required repairs to the beach protection between the Ad. Building and the Grebe cottage.

1974- September 1

100. To have repairs made to sea wall near tennis court area and immediately north using bolted construction for whalers and material 10 to 12 feet deep.

1980- October 31

283. That the Executive Board be given authority to approve “jetty” work at Weiherman Park and that balance of projects be prioritized and cost estimated for presentation to March 1981 Board meeting.

1981- October 30

325. To authorize $25,000 (if needed and not to exceed) for capital expenditures for store, added maintenance and shoreline protection.

1982- September 24

362. To authorize Dick Korthals to work with an appropriate ACCA representative and possibly a representative from the Starke Point to act on our behalf and approach the Corps of Engineers with the request that dredged sand be transported further north than it is at present time.

1983- May 29

378. To revoke the authorized expenditure for the craft shop remodeling and divert these funds to protecting the beach area. Funds to $35,000 authorized. High water was causing problems.

1983- November 4

385. That LCA continue its cooperation with ACCA in efforts for shoreline protection at Weiherman Park by sharing equally the administration, cost and use of such protection

1984- November 2

432. To ratify expenditure of $8,500 above approved budget for work already installed. (jetty)
442. To proceed with getting materials for up to $9,000 for jetty work

1985- April 13

455. To authorize Raymon Frost to proceed as necessary to protect the cement seawall and restore the beach, making substitutions in previously approved expenditures and spending up to $10,000 more if necessary to preserve the camp property.

1985- May 25

461. To allocate $11,000 more for Randall to complete his jetty work; his amount to include a bonus of $3,000 if completed by July 4,
462. To approve an additional $16,000 above the remainder of the amount authorized in April to install 150’ of reinforced steel seawall with a channel iron cap north of the pier in front of the Inn, and 450’ of wooden seawall south of the pier, the entire area to be backfilled

1985- October 25

468. To approve the further expenditure of $15,000 for incremental costs incurred this year for jetties.

1986- May 24

485. About 500 cubic yards of sand are needed to form a safe slope from the cement seawall towards the forward seawall from the observation deck to the center of the patio. Allen Domres of Onekama has offered to do the work, partially as a donation, for $2/yard. The Board approved spending the money for the sand, sending Domres a letter of thanks, and inviting the Domres family for dinner as an expression of our appreciation.
486. To approve expenditure of up to $5,000 for the LCA’s share of the protection of Weiherman park by the revetment process.
487. Dick Blum presented a request tat LCA be guarantor if ACCA found it necessary to borrow money to meet project payment dates. It was moved that LCA be guarantor of the proposed $50,000 line of credit, with written proposals, including encumbrances, to be provided and made a matter of record. Dick Blum proposed a modification, which Kienman accepted: Moved that LCA be guarantor of the proposed $50,000 line of credit. ACCA will, in turn, provide suitable collateral in terms of personal notes or liens against property should any such borrowing take place. This matter to be subject to the approval of counsel.

1986- May 24

496. To authorize funds up to $50,000 for shoreline protection work in the 1986 season.

1986- November 7

501. That the board ratify several actions of the executive committee:
2) Additional expenditures for shoreline protection during the season.
502. To direct Ray Frost to determine what we can do to meet the Health Department regulations and proceed based on that information. (Relating to the septic tanks filling with ground water due to the high lake levels. Septic system was pumping more groundwater than wastewater.)
503. That Ray be authorized, up to $20,000, in conference with the Executive Committee, to allow us to operate in 1987. This includes current sump pumping upgrade, hydrologist fee, de-watering installation, replacement of septic tanks, and shoreline protection in front of the buildings.
507. To authorize funds up to $10,000 from the General Fund for reinforcement of the revetment

1987- April 4

521. To ratify the Executive Committee expenditure of $4,500 over the budgeted amount for the revetment improvements.
527. To authorize an additional $25,000 (above the $30,000 authorized in November) to complete the authorized projects. (De-watering system and septic system)
528. To authorize that 1,000 cubic yards of sand at a cost not to exceed $2,000 should be placed in front of the Inn north of the concrete pier: The money to pay for this will come from the Forward Fund.

Camp Arcadia continues to thrive as a great place to become renewed in body, mind and spirit. However, continuing to preserve this place comes at a cost. The generosity of the LCA membership is one of the main reasons that Camp has continued to thrive. As a board, we are currently in the process of trying to find the best possible long-term solution to our beach issue. We hope to find a system that will enable us to protect our buildings, provide us with a naturally accreted beach which will be easily accessible to our guests and also will have the least adverse affect on our neighbors to the north and to the south.

back to top


  Contact information for Camp Arcadia and Beach Erosion Committee.
Go to Camp Arcadia's home website.